For an off-plan buyer, "completion" is the word everything waits for. It is also easy to misread. A building can look finished long before it is complete in the sense that matters, and completion is not the same as handover or the title deed. This guide explains what completion means, what the completion certificate is, and what follows it. It describes Dubai.

What the completion certificate is

A building is complete, in the sense that matters, when the licensing authority issues its completion certificate. Which authority that is depends on where the project is. The Dubai Development Authority, for example, describes its building completion certificate as one issued according to the approved drawings and designs, and asks for a set of inspections and approvals before it is issued, among them a certificate from Civil Defence.

In short: the certificate is meant to confirm that the building was built as it was approved to be built, and has passed the checks that come with that.

What it is not

What follows it in Dubai

Once the completion certificate is issued, several things follow. These steps do not always happen in this order.

  1. The completed project is registered. The Land Department says that once the developer receives the completion certificate, it must register the completed project. Dubai's Law No. 13 of 2008 says the same: developers must enter completed projects in the Property Register once they receive the certificate.
  2. The documents go to the Land Department. For a building with shared parts, Dubai's law on jointly owned property says the developer must file its plans and the documents that govern it with the Land Department within sixty days of the completion certificate. The Department may allow up to thirty days more.
  3. Your unit moves to the Real Estate Registry. The Department says units that have been fully paid for move from the initial register to the Real Estate Registry, and the owner receives a title deed, or, in an area of long-term leases, a usufruct certificate. Our guide to title deeds explains how to check one.
  4. The escrow account is closed in stages. Dubai's escrow law says that once the completion certificate is issued, the escrow agent holds back part of the account, and releases it to the developer one year after the units are registered in the buyers' names. Our guide to escrow accounts explains what that account is for.
  5. Handover. You receive the keys, after the checks our guide to handover day describes.

When the structural defect period starts

Completion also starts a clock. Under Dubai's law on jointly owned property, a developer's responsibility for defects in the structural parts of a building runs from the date of the completion certificate. The period for faulty installations, such as electrical and plumbing work, runs from handover instead. Our guide to defects after handover explains both.

Questions to ask

  1. Has the completion certificate been issued, and on what date?
  2. When will the completed project be registered with the Land Department?
  3. What remains for me to pay before my unit is registered in my name?
  4. When will handover begin, and how will I be told?
  5. Where will I connect electricity and water, and what will I need? Our guide to moving in covers it.

A word on dates

A project's expected completion date may be an estimate. What binds the developer is what your contract says about completion and about delays, so read it before you sign. The completion certificate shows when the building was actually certified.

Where diar.tv stands

diar.tv shows LIVE launches and LIVE Viewings of homes, presented live, or as premieres, by government-approved, verified agents. It does not issue certificates, register projects or hold money. Registering interest on diar.tv is a non-binding first step. This guide is not legal advice: the laws, the Land Department and the licensing authority are the authority.

The short version

A building is complete when the licensing authority issues its completion certificate, which says it was built as approved. In Dubai, the developer then registers the completed project and files its documents with the Land Department; fully paid units move to the Real Estate Registry and title deeds are issued; part of the escrow account is held back for a year; and handover follows, though not always in that order. Ask for the certificate's date: some of the developer's responsibilities run from it.